The regular hours for each workday is from 8:30am to approx. 4:00pm.
Age Restrictions: Under 16 yrs old: Must be closely supervised by a parent
16,17 yrs old: Cannot operate power tools or be on roof
18 and older: Allowed to attempt it all
For more information, contact: Chuck Anderson at 765-491-8200 or andercr.55@comcast.net.

| Date | Job | Volunteers |
| Sept. 8th Wednesday | ||
| Roofing | Professional | |
| Rough-in inspection - pm | _ | |
| Insulate perimeter walls after inspection | volunteer | |
| Tear out front steps | _ | |
| Sept. 9th Thursday | ||
| Insulate perimeter walls ,and hang ceiling drywall | Lead Hangar | |
| Energy inspection - pm | _ | |
| Begin hanging wall drywall | _ | |
| Paint doors and trim offsite | volunteer | |
| Cleanup in the pm | volunteer | |
| Sept. 10th Friday | ||
| Hang wall drywall | Lead Hangar | |
| Hang siding | Jon Kolhoff | |
| Sept. 11th Saturday | ||
| Hang wall drywall | John Sears | |
| Hang Siding | jenny megalli | |
| Paint doors and trim offsite | Amy Carey | |
| Sept. 14th Tuesday | ||
| Drywall finishing | Professional | |
| Hang siding | volunteer | |
| Sept. 15th Wednesday | ||
| Drywall finishing | Professional | |
| Hang siding | Justin McCloskey | |
| Sept. 16th Thursday | ||
| Drywall finishing | Professional | |
| Hang siding | volunteer | |
| Sept. 17th Friday | ||
| Drywall finish texturing | _ | |
| Hang siding | Brian Rosko | |
| Sept. 18th Saturday | ||
| Sand drywall, clean up, prime & paint - am | Jacob M. Engle | |
| Finish coat - pm | Nathan Fuller | |
| Sept. 21st Tuesday | ||
| Install underlayment/cement board, hang doors & trim | Elizabeth Lehmann | |
| Sept. 22nd Wednesday | ||
| Install vinyl | St. Boniface | |
| Sept. 23rd Thursday | ||
| Trim carpentry, doors, cabinets | Lead installer (Pro), Lead installer (Pro), Jacob M. Engle | |
| Cleanup in the pm | volunteer | |
| Sept. 24th Friday | ||
| Trim carpentry, hang cabinets, install counter tops | Brian Auffart, Lead installer (Pro) | |
| Sept. 25th Saturday | ||
| Plumbing trimming | Brian Auffart, Hannah Burgess | |
| Insulate attic | Habitat, Anne Krasniak | |
| Final grading | Professional | |
| Sept. 27th Monday | ||
| HVAC final install | Mark Robert's Lafayette HVAC | |
| Sept. 28th Tuesday | ||
| Electrical trimming | Bob Roswarski' crew | |
| Landscaping | Lafayette Lawn -Terry Keach | |
| Sept. 29th Wednesday | ||
| Lawn | Lafayette Lawn & Shrub | |
| Sept. 30th Thursday | ||
| Clean floors for carpeting | volunteer | |
| Oct.1st Friday | ||
| Carpeting | Professional (Vol.) | |
| Blinds | Professional (Vol.) | |
| Electrical Inspection, | _ | |
| Energy Star Inspection | _ | |
| Oct.2nd Saturday | ||
| Finish cleanup, touch-up, punch list, house numbers, etc... Good detail people needed. | Jon Kolhoff |